Contract 1: Heavy Civil and Airfield Lighting
Approximately 91% of contract is complete with 77% of the contract time used.
Contract 2: Terminal Building, ATCT and Support Buildings
Approximately 40% of the contract is complete with 48% of the contract time used.
Terminal:
Approximately 49% of contract work is complete with 54% of the contract time used. All interim milestones are being met or exceeded.
Main Access Road:
24″ Water Main is 98% complete.
GA Access Road:
Approximately 91% of contract is complete with 77% of the contract time used.
- 40% of the edge lighting on the Runway and Taxiways is complete.
- Phoenix has submitted a plan to DEP for draining the 75 acre pond.
- There are 43 people working in Morrell Branch restoring the area and removing silt.
- Another 25 people are performing the same type work in Kelly Branch.
Contract 2: Terminal Building, ATCT and Support Buildings
Approximately 40% of the contract is complete with 48% of the contract time used.
Terminal:
- Exterior sheathing all areas is 75% complete.
- Roof sheathing and underlayment all areas is 95% complete.
- Beginning installation of CMU walls in Baggage Handling area.
- Continuing mechanical/electrical and plumbing work.
- Continuing MEP work through Level 4.
- Continuing interior framing of Air Maintenance Facility and Air Maintenance Shed.
- Continuing with the installation of exterior wall panels and installation of electrical in Air Cargo Facility.
- Continuing with plumbing and electrical rough-in.
- Began compacting and prepping for Slab on Grade.
- Completing metal decking and installing stairs.
- Continuing installation of CMU at vehicle bay.
- An average of 165 personnel are on site Monday through Friday.
- 9 workers on site on Saturday.
Approximately 49% of contract work is complete with 54% of the contract time used. All interim milestones are being met or exceeded.
Main Access Road:
- 3W2″ Power Distribution Duct Bank: 95% complete
- Installation of wiring by Gulf Power.
- Street Light Duct Work is 94% complete.
- Wire being pulled.
- Boxes being installed.
- 6W4″ Power Distribution Duct Bank: 100% complete.
- Jack and boring on Main Access Road for fire hydrant installation.
24″ Water Main is 98% complete.
GA Access Road:
- 12″ water main is 96% complete.
- 30″ water main is 86% complete.
- Lift station is 50% complete.
- Plumbing being installed
- Fuel farm is 15% complete.
- Electrical work in progress.
- Booster station is 35% complete.
- Concrete roofs being installed.
- Triturator is 10% complete
- Vault installation in progress
- Continuing to collect and transplant Juncus plants to wetlands area in Kelly Branch.
- Disking and limerock on Main Access Road to begin on Thursday August 5th.
- Seeding of Main Access Road scheduled for Monday August 10th.
- ValleyCrest to use erosion control matting where necessary along Main Roadway.