Contract 1: Heavy Civil and Airfield Lighting
Approximately 91% of contract is complete with 80% of contract time used.
Approximately 47% of contract is complete with 52% of contract time used.
Terminal:
Approximately 57% of contract work is complete with 54% of contract time used.
Approximately 7% of the work is complete with 11% of the contract time used.
Approximately 91% of contract is complete with 80% of contract time used.
- Pond C grading is 99% complete.
- Installing Airfield Edge Lighting Conduit and Plazas
- Continuing installation of Airside underdrain pipe
- Terminal Apron concrete pad is complete
- Morrell and Kelly Branch restoration continues
Approximately 47% of contract is complete with 52% of contract time used.
Terminal:
- In the utility area completed form work and compaction and preparing for concrete pour.
- Continuing metal framing on 1st and 2nd levels.
- In the baggage handling area continuing exterior CMU walls. Work is 60% complete.
- Preparing for concrete pour of stairs and deck Levels 2,3 and 4.
- Installing decking and metal stairs floors 5-9.
- Air Maintenance Facility - continuing electrical rough-in walls at maintenance office and bays.
- Air Cargo Facility - continuing with the installation of MR gypsum wall board.
- Beginning the erection of the pre-engineered metal building.
- Continuing block installation at 2nd level administration area.
- An average of 155 personnel are on site Monday through Friday and approximately three workers are on site on Saturday.
Approximately 57% of contract work is complete with 54% of contract time used.
- 3W2″ Power Distribution Duct Bank is 95% complete; installation of wiring by Gulf Power is ongoing.
- Street Light Duct Work is 98% complete; light poles being installed (approx. 6-8 per day).
- 6W4″ Power Distribution Duct Bank is 100% complete.
- Jack and boring on Main Access Road for fire hydrant installation.
- 24″ Water Main is 98% complete.
- 12″ water main is 99% complete.
- 30″ water main is 90% complete; installation continuing on the utility road.
- Lift Station is 50% complete; plumbing is being installed.
- Fuel Farm is 25% complete; electrical work is in progress.
- Booster Station is 40% complete; concrete roofs are poured.
- Triturator is 10% complete; vault installation is underway.
Approximately 7% of the work is complete with 11% of the contract time used.
- Construction is underway on overflow weirs on Main Access Road
- Performing soil preparation on Main Access Road.
- Hydro seeding of Main Access Road is underway.
- Installing aquatic plants at main entrance.