Construction Update: 4/16/2009
Posted: 20 Apr 2009 09:02 PM PDT
Contract 1: Heavy Civil and Airfield Lighting
Approximately 86% of the contract work is complete with only 60% of the contract time used.
Contract 2: Terminal Building, ATCT and Support Buildings
Approximately 22% of contract work is complete with 31% of contract time utilized.
Terminal:
Contract 3: Utility Contract
Approximately 26% of contract work is complete with 25% of contract time utilized.
Main Access Road:
Posted: 20 Apr 2009 09:02 PM PDT
Contract 1: Heavy Civil and Airfield Lighting
Approximately 86% of the contract work is complete with only 60% of the contract time used.
- Installation of underground utilities continues in the General Aviation area; approx. 80 % complete.
- 8400’ of Runway 16-34 is 100% complete. (Still awaiting final approval for 10,000’).
- Earthwork, sub grade and limerock base is complete on Taxiway D; Asphalt paving is approximately 60% complete.
- Masonry work is ongoing on the ALV building.
- Installation of the centerline lighting cans is approximately 82% complete.
- TDZ lighting cans are approx. 81% complete.
Contract 2: Terminal Building, ATCT and Support Buildings
Approximately 22% of contract work is complete with 31% of contract time utilized.
Terminal:
- Beginning installation of roof deck in Area A.
- 2nd floor is now complete in Area B.
- Continuing installation of reinforcing steel in area D 2nd level.
- Continuing installation of underdrains.
- Slab on grade is complete between columns B & C in Area A.
- Continuing with structural steel sequence in Area A.
- Completed concrete pour of foundation walls.
- Completed slab on grade and now erecting steel.
- Continuing installation of split face CMU walls.
- Continuing installation of split face CMU walls; setting door frames.
- Completing installation of underground utilities.
- Forming, resteeling and pouring elevator walls.
Contract 3: Utility Contract
Approximately 26% of contract work is complete with 25% of contract time utilized.
Main Access Road:
- 3W2” Power Distribution Duct Bank: 68% complete.
- Street light duct work: 75% complete.
- 24” water main: Testing complete-passed.
- 30” water main: 55% complete.
- Wet well installed.
- 8” Directional Drill is complete