Sealed bids for County Road 30A Resurfacing Project will be received by the Board of County Commissioners , Walton County, Florida, hereinafter referred to as "County" at the Office of Central Purchasing, 176 Montgomery Circle, DeFuniak Springs, FL 32435.

Closing date is October 3, 2016 no later than 10:00AM local time and will open immediately thereafter.

All questions are to be directed in writing to the County Purchasing Agent. Questions must be submitted to Purchasing no later than 12:00 Noon on September 22, 2016. DIRECTION QUESTIONS TO ANY OTHER COUNTY STAFF, PROJECT ENGINEER, OR ANY OTHER PERSON IS PROHIBITED AND WILL RESULT IN BID BEING DISQUALIFIED.

PROJECT: The Walton County Road 30A Resurfacing Project is located in Santa Rosa Beach within sections 1, 2, and 12 of township 3S and range 20W. The scope of the proposed project will involve roadway rehabilitation along CR 30A between its intersection with CR 393(S) and CR 83(S). As part of this project, the contractor will be required to mill and remove existing asphalt pavement to and average depth of two inches throughout the project limits followed by completion of a two inch hot mix overlay. The contractor will be required to provide Maintenance of Traffic throughout the duration of construction and will be responsible for coordinating, inventorying, and replacing all pavement striping and markings damaged or removed during the construction process. Clipping of shoulders will be required prior to completion of the roadway rehabilitation efforts.

BIDDER IS RESPONSIBLE FOR THE DELIVERY OF ITS BID. BIDS RECEIVED AFTER THE SPECIFIED DAY AND TIME WILL NOT BE OPENED. OUR AREA IS NOT A GUARANTEED OVERNITE FEDEX DELIVERY. LOCAL MAIL IS NOT DELIVERED UNTIL AFTER 3:00PM DAILY.

PACKAGES SHALL BE SUBMITTED TO THE OFFICE OF CENTRAL PURCHASING ONLY TO ENSURE RECEIPT OF SAID PACKAGE.

PURCHASING DEPARTMENT IS CLOSED ON FRIDAY.

LATE SUBMITTALS RECEIVED AFTER THE FOREMENTIONED DEADLINE DATE, EITHER BY MAIL, OR OTHERWISE, WILL NOT BE CONSIDERED AND RETURNED UNOPENED. THE TIME OF RECEIPT WILL BE DETERMINED BY THE TIME RECEIVED IN THE PURCHASING AGENT’S OFFICE. IT IS THE SOLE RESPONSIBILITY OF THE FIRM FOR ASSURING THAT THE ITB IS RECEIVED IN THE PURCHASING OFFICE BY THE DESIGNATED DATE AND TIME. NO FAXED, ELECTRONIC OR ORAL ITB WILL BE ACCEPTED

To be considered, Firm/Team must submit an original and five (5) copies of ITB in a sealed envelope or package, clearly marked with the Firm/Team’s name and address, and the words "County Road 30A Resurfacing Project” addressed to Office of Central Purchasing.
 
Last edited:

jodiFL

Beach Fanatic
Jul 28, 2007
2,466
741
SOWAL,FL
Title says 395 but the document says 393. I cant figure out why they would do this now, dont they have bridges that need repairing between 393 and 83?
 

Kurt

Admin
Oct 15, 2004
2,332
5,037
SoWal
mooncreek.com
C.W. Roberts will begin construction activities for asphalt milling, resurfacing and restriping approximately 2.2 miles of CR 30A from CR 393 to CR 83.

This project is scheduled to begin mid-January and is anticipated to be completed within 30 calendar days. During this construction period the road will remain open to traffic; however the public may encounter slight delays and may encounter lane restrictions. Motorist and Pedestrians are encouraged to use caution while traveling in this area.

All planned construction activities are weather dependent and may be rescheduled in the event of inclement weather. For more information regarding this project, please contact Public Works at (850) 892-8108.
 

John G

Beach Fanatic
Jul 16, 2014
1,800
553
Lets give some props to our Road Department. They have done a good job with what they are TOLD to do.
They don't make the decisions. They have returned my calls and are responsive. I believe most are good folks that do a good job and don't want to buck the system.

Just like when they are told to pave a dirt road up in the north end where a deputy might live, they do it.

They are just foot soldiers doing what they are told and they do a good job.

I think Dangerous C. Jones (DCJ) got rid of one back in the day she didn't like...
 

Truman

Beach Fanatic
Apr 3, 2009
654
276
Most of the time, a road leads to a destination. Scenic 30A is a destination.

We don't want markers signs and utilities on our beaches, nor should we on Scenic 30A.
 
New posts


Sign Up for SoWal Newsletter