Bear Creek Phase III - Request to approve by final order. Project number
MAJ18-000013 is being reviewed by Bob Baronti. This is a major
development order application submitted by Morris-Depew Associates,
Inc., on behalf of JMB Freeport, LLC, requesting approval to subdivide four
parcels into 351 residential lots on 219.15 +/- acres with a future land use
of Rural Village. The project is located approximately 1200 feet south of the
intersection of Fluffy Landing Road and Bear Creek Blvd., and is identified
by parcel number(s) 02-2S-19-24000-018-0000,
03-2S-19-24000-001-0000, 03-2S-19-24000-001-0050,
03-2S-19-24000-001-0080. (Continued from 11/20/18)
Attachments: Bear Creek PH III Agenda Request Form 12-18-18
MAJ17-000013_Bear Creek PH III BCC StaffReport 12-18-18
Bear Creek - Major DO - Insert Package - 12-10-18 (1)
MAJ18-000013_Bear Creek PH III Final Order 12-18-18
❖ Discussed drainage system as there are issues with flooding in this area
❖ A nearby property owner expressed concerns about this development adding to flooding issues
in the area and requested that there be consideration by the county to redesign 3280 to alleviate
the flooding vs. just resurfacing the road.
❖ Phase IIIA, the technical submittal, was approved unanimously.
❖ Phases IIIB through IIIF were being considered for conceptual approval. They were continued to
the 2/28/19 meeting
Looks to be about 1,000 homes when built out.
Bear Creek Phase III - Request to approve by final order. Project number
MAJ18-000013 is being reviewed by Bob Baronti. This is a major
development order application submitted by Morris-Depew Associates,
Inc., on behalf of JMB Freeport, LLC, requesting approval to subdivide four
parcels into 351 residential lots on 219.15 +/- acres with a future land use
of Rural Village. The project is located approximately 1200 feet south of the
intersection of Fluffy Landing Road and Bear Creek Blvd., and is identified
by parcel number(s) 02-2S-19-24000-018-0000,
03-2S-19-24000-001-0000, 03-2S-19-24000-001-0050,
03-2S-19-24000-001-0080. (Continued from 11/20/18)
Attachments: Bear Creek PH III Agenda Request Form 12-18-18
MAJ17-000013_Bear Creek PH III BCC StaffReport 12-18-18
Bear Creek - Major DO - Insert Package - 12-10-18 (1)
MAJ18-000013_Bear Creek PH III Final Order 12-18-18
❖ Discussed drainage system as there are issues with flooding in this area
❖ A nearby property owner expressed concerns about this development adding to flooding issues
in the area and requested that there be consideration by the county to redesign 3280 to alleviate
the flooding vs. just resurfacing the road.
❖ Phase IIIA, the technical submittal, was approved unanimously.
❖ Phases IIIB through IIIF were being considered for conceptual approval. They were continued to